When loads get too big for forklifts and too precise for rough handling, teams turn to overhead cranes. This long-form walkthrough takes you behind the scenes of a mega-project crane install. You’ll see preparation and surveys—all explained in clear, real-world language.
Bridge Crane Basics
An overhead crane rides on parallel runways anchored to a building frame, carrying a trolley-mounted hoist for precise, vertical picks. The system delivers three axes of motion: cross-travel along the bridge.
They’re the backbone of heavy shops and assembly lines, from beam handling to turbine assembly.
Why they matter:
Safe handling of very heavy, unwieldy loads.
Huge efficiency gains.
Repeatable, precise positioning that reduces damage.
High throughput with fewer ground obstructions.
What This Install Includes
Runways & rails: continuous beams and rail caps.
End trucks: motorized gearboxes for long-travel.
Bridge girder(s): single- or double-girder configuration.
Trolley & hoist: reeving, hook block, upper limit switches.
Electrics & controls: power supply, festoon or conductor bars.
Stops, bumpers & safety: overload protection, e-stops.
Depending on capacity and span, you may be dealing with modest shop lifts or major industrial picks. The installation flow stays similar, with heavier rigs demanding extra controls and sign-offs.
Pre-Install Prep
A clean install is mostly planning. Key steps:
Drawings & submittals: Freeze the GA and verify reactions with the structural team.
Permits/JSAs: Permit-to-work, hot work, working at height, rigging plans.
Runway verification: Survey columns and runway beams for straightness, elevation, and span.
Power readiness: Lockout/tagout plan for energization.
Staging & laydown: Mark crane components with ID tags.
People & roles: Appoint a lift director, rigger, signaler, and electrical lead.
Millimeters at the runway become centimeters at full span. Measure twice, lift once.
Rails & Runways
If rails are off, nothing else kk construction will run true. Targets and checks:
Straightness & elevation: shim packs under clips to meet tolerance.
Gauge (span) & squareness: Use feeler gauges on splice bars, torque rail clips.
End stops & buffers: Verify clearances for bumpers at both ends.
Conductor system: Mount conductor bars or festoon track parallel to the rail.
Log final numbers on the ITP sheet. Misalignment shows up as crab angle and hot gearboxes—don’t accept it.
Putting the Span in the Air
Rigging plan: Softeners protect painted flanges. Taglines for swing control.
Sequence:
Lift end trucks to runway level and set temporarily on blocks.
Rig the bridge girder(s) and make the main lift.
Land the bridge on the end trucks and pin/bolt per GA.
Verify camber and bridge square.
Before anyone celebrates, bump-test long-travel motors with temporary power (under permit): ensure correct rotation and brake release. Lock out after test.
Hoist & Trolley
Trolley installation: Mount wheels, align wheel flanges, set side-clearances.
Hoist reeving: Check rope path, sheave guards, and equalizer sheaves.
Limits & load devices: Set upper/lower limit switches.
Cross-travel adjustment: Align trolley rails on a double-girder.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
Grinding noises mean something’s off—stop and inspect. Fix the mechanics first.
Drive Tuning & Interlocks
Power supply: Drop leads tagged and strain-relieved.
Drive setup: Program VFDs for soft starts, decel ramps, and brake timing.
Interlocks & safety: Zone limits near doors or mezzanines.
Cable management: Secure junction boxes; label everything for maintenance.
Future you will too. If it isn’t documented, it didn’t happen—put it in the databook.
QA/QC & Documentation
Inspection Test Plan (ITP): Hold/witness points for rail alignment, torque, electrical polarity, limit settings.
Torque logs: Record wrench serials and values.
Level & gauge reports: Note any corrective shims.
Motor rotation & phasing: Confirm brake lift timing.
Functional tests: Jog commands, inching speeds, limits, overloads, pendant/remote range.
QA/QC is not paperwork—it’s your warranty in a binder.
Ready for Work
Static load test: Apply test weights at the hook (usually 100–125% of rated capacity per spec).
Dynamic load test: Check sway, braking distances, and VFD fault logs.
Operational checks: Limit switches trigger reliably; overload trips; horn/beacon function.
Training & handover: Maintenance intervals for rope, brakes, and gearboxes.
When the logbook is clean, the crane is officially in service.
Where These Cranes Shine
Construction & steel erection: placing beams, trusses, and precast.
Oil & gas & power: moving heavy pumps, skids, and pipe spools.
Steel mills & foundries: large part transfer.
Warehousing & logistics: bulk material moves with minimal floor traffic.
Floor stays clear, production keeps flowing, and precision goes up.
Safety & Engineering Considerations
Rigging discipline: dedicated signaler and stop-work authority.
Lockout/Tagout: test before touch every time.
Fall protection & edges: approved anchor points, guardrails on platforms, toe boards.
Runway integrity: regular runway inspection plan.
Duty class selection: overspec when uncertainty exists.
A perfect lift is the one nobody notices because nothing went wrong.
If It Doesn’t Run Smooth
Crab angle/drift: verify end-truck wheel diameters and gearbox mounts.
Hot gearboxes: misalignment or over-tight brakes.
Rope drum spooling: check fleet angle and sheave alignment.
Pendant lag or dropout: shield noisy VFD cables.
Wheel wear & rail pitting: add rail sweeps and check clip torque.
A 10-minute weekly check saves days of downtime later.
Quick Answers
Overhead vs. gantry? Bridge cranes ride fixed runways; gantries walk on the floor.
Single vs. double girder? Singles are lighter and cheaper; doubles carry heavier loads and give more hook height.
How long does install take? Scope, bay readiness, and tonnage rule the schedule.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
Why Watch/Read This
If you’re a civil or mechanical engineer, construction manager, shop supervisor, or just a mega-project fan, this deep dive makes the whole process tangible. You’ll see how small alignment wins become big reliability wins.
Want ready-to-use checklists for runway surveys, torque logs, and load-test plans?
Grab the installer pack so your next crane goes in cleaner, faster, and right the first time. Save it to your site tablet for quick reference.
...
Read more arabic articles...
read more about this products